25 Aug 2014
Window Glazing
8 windows to be glazed by hubby and myself...the first one took 1.5 hours, and following windows approximately one hour each, experts by the time all were glazed and trimmed.
21 Aug 2014
Fitting roof and sky lantern
After much discussion we decided to employ a roofing company to fit the timber frame and roof lantern, and after seeing the amount of timber and quality of their work, we are really pleased we chose to go this route
By end of day one the roof construction is complete, and first coat of fibre glass coating has been applied and left to dry
Work completed end of day two, with second coat of fibreglass and roof lantern fitted and glazed
By end of day one the roof construction is complete, and first coat of fibre glass coating has been applied and left to dry
Work completed end of day two, with second coat of fibreglass and roof lantern fitted and glazed
There followed some touch up painting and trimming by hubby
Fitting Woodwork to Conservatory
The next step in conservatory construction is to erect the woodwork panels etc.
First step is the fitting of the exterior and interior sills and door frame, followed by the installation of the window frames. As we are adapting the purchased units to fit into our plan, we needed to cut off 10mm down the length of several of the windows, to ensure the 5 windows fitted along the length of the conservatory. We hired a table saw to make this job easier.